New Construction

Construction Milestones

Stage 0

Pre-construction Activities
  • Scrape Lot - order trusses/lumber - erosion control
  • Should be completed on or near E1 start date

Stage 1

Slab complete
  • Underground plumbing is done - concrete is poured - lot is rough graded
  • Should be no more than 2 weeks from stage 0

Stage 2

Frame complete
  •  Frame is complete - roof dried in - house wrap - windows may or may not be installed
  • About 2 weeks from stage 1

Stage 3

Frame inspection
  • Rough mechanicals complete  -exterior cladding may be started. May include Insulation
  • Should be 2-3 weeks from stage 2 depending on size of home

Stage 4

Drywall complete
  • Drywall and exterior cladding complete - underground utilities
  • Should be 2 weeks from stage 3 - maybe 3 depending on size of home

Stage 5

Cabinets complete
  • Cabinets installed - paint and trim - garage door
  • Should be 2 weeks from stage 4 if incorporating paint and trim in the stage

Stage 6

Tops installed
  • Granite, vanities, MEP trim, wet floors, shower tile - driveway and final grade
  • 10 days from stage 5

Stage 7

Flooring complete
  • Carpet, hardwood, bath accessories, landscape
  • 1 or 2 weeks from stage 6

Stage 8

Quality Assurance - Home is 100%
  • Inspections - power - energy star - point up
  • 1 week from stage 7

Stage 9

Warranty handoff - closed home
  •  Orientation and Closing 100% complete
  • In Nashville - this is 10 days from stage 8
    • 16 weeks +/- (112 - 120 days)